top of page
Arnett Avenue 15.06.2021_027.jpg

Latest News 

April 2024

Project Completed! A fantastic project taking existing training facilities from a grade D to C. Works consisting of a new club house building with extensions to the main stand, extensions and modifications to the existing covered seating, new turnstiles and modifications to existing fencing.

.

January 2024

As we waved good bye to 2023 we saw the completion and handover of our site in Royal Wootton Bassett for RWB Auctions. Taking this large existing supermarket and turning it into a smart, sophisticated auction house has been a pleasure. It's a job we're incredibly proud to have sitting in our home town. All of us at Leighfields wish Max, Jon, Steve and everyone else involved all the very best in their new home.

December 2023

Excellent progress is being made on site in Wheatley for Soha Housing. The site has now really started to take shape with the foundations complete and blockwork well underway.
Excellent progress at the site in Winklebury as well for Basron Developments Ltd & Basingstoke Town Football Club with the roof cladding now complete, the scaffold dropped and the internals really taking shape.

We'd like to take this opportunity to wish our clients and contractors a very merry Christmas and a prosperous 2024.

November 2023

Some great progress being made on site in South Marston for Les Smith Haulage. The concrete pour for the main yard has commenced. A superb flagship home motoring towards completion.

October 2023

Progress is going well at the Basingstoke FC facilities. The newly installed drainage is well underway, and the final touches of the Club House structure are being finished off with the installation of the cold rolled steel. Next, we are preparing to move onto the substructure masonry. The stand enhancements have begun, both concrete pads have been poured and the South Stand amendments have started. The 6-Tier stand is in the progress of being replaced with a larger 8-Tier standing stand.

August 2023

Contract Awarded.

R J Leighfields have been successful in securing the contract to upgrade and enhance the existing training facilities for Basingstoke Football Club. Works comprise of a single storey extension to existing main stand and the construction of a new clubhouse with associated works.

July 2023

Works have been completed at our site of 10 houses in Oxford and handed over to our client Oxford City Housing.

June 2023

Contract Awarded.

Leighfields have been awarded the contract for the design and construction of a zero carbon development of 12nr dwellings in Wheatley, Oxford.

Works are also progressing well at the new flagship head office and depot for Les Smith Haulage in South Marston, with the steel frame being erected.

March 2023

Some fantastic progress being made on site in Oxford with the external render complete, interior decorations progressing nicely and kitchens being installed. A busy site with the end in sight.

February 2023

Some of the latest shots from our site in Oxford.

November 2022

Contract Awarded.

An exciting appointment for R J Leighfield & Sons Ltd working with the local business RWB Auctions. The redevelopment of a former supermarket into a modern auction house consisting of two auction rooms, a cafe/bistro with an upstairs art gallery and roof terrace.

September 2022

May 2022

We’ve begun on site the construction of 10 three-bedroom houses, including associated drainage, external works and external services.

Floor Plans.jpg

April 2022

We’ve been appointed by Wishford Schools Group Ltd to complete refurbishment of the former care home into a 34 bed boarding house for Westonbirt School. It’s a 20 week project that involves strip out, layout changes, M&E works, redecoration and floor finishes throughout the building.

February  2022

R J Leighfield completes the renewal of our investors in people accreditation. Investing in our staff is part of our identity and crucial to our outstanding retention stats. With the help of Investors in People we able to keep providing our staff with a great environment to work 

November 2021

All properties at Rowley Mews have now been handed over. these works comprised of constructing 9x 3 Bed 2.5 storey townhouses on a brownfield site using timber frame construction. For more information on this scheme click HERE

October 2021

Arnett Avenue Handed over. This project comprised the design and build of 10 houses, 3 for shared ownership and 7 for rent, 36 flats of which 20 were shared ownership and 16 for rent. The site was formerly occupied by sheltered accommodation and bungalows. for more infomation on this scheme click HERE

bottom of page